Build: 2013 02 11 – 17; Week 03

Friday 15: Concrete is poured into the lower level roof Рthe garage roof is already finished. The props used are professional, unlike many building sites where wooden poles are cut, supposedly to the same length.

Thursday 14: The hole for the rain water tank is finished off – the ‘bagger’ can’t handle neat corners of a smooth base. In a short time, the base is formed!

Tuesday 12 & Wednesday 13: Heavy rain on both days made any serious work impossible. The guys have worked non-stop for the past two weeks, so a rest is necessary anyway, in our opinion.

Monday 11: The earth from the last part of the retaining wall, from the technical room to the south-west end of the site, along the road is cleared.